New Addition Project
New Addition Project
Projected Start: Spring of 2021
Projected Cost: $500,000
Actual cost $600,000
Groundbreaking Ceremony: April 11, 2021 at 11AM


Groundbreaking Ceremony: 4/11/21



Moving Dirt Officially Begins
April 28th 2021






Foundation Poured



Building and Pouring of Walls



.jpg)
Preparing the Floor: June 2021




Pouring the Floor: July 7, 2021




Walls for the kitchen, and bathroom and storage areas going up




Rafters set in place



Major Setback




Clean-up begins



Second Time Around


Exterior Siding Completed



We have Electricity

Interior Work







.jpg)





Hanging of the Sign